SUMMARY


SEPTEMBER 2025




The façade is now 90% complete, with a new perimeter wall that enhances the project’s visual appeal and market presence. Interior budgeting for the lobby and common areas is underway, and garage works are scheduled to begin soon. The project remains on track with the updated plan.
AUGUST 2025



JULY 2025


Despite some delays related to the façade and elevator installations, which required us to adjust the construction timeline, progress continues across multiple fronts. We now anticipate a realistic project completion and unit delivery by early 2026.
On a positive note, Apartment S was successfully sold during this period, and we are working on a refreshed and more luxurious visual identity for the fencing and façade, which will be shared in the next update.
JUNE 2025