SUMMARY


AUGUST 2025
Construction is advancing with significant milestones achieved, including the installation of EIFS finishes, third-floor roll-up doors, lighting systems, fire alarm wiring, and HVAC connections. The project continues to progress on schedule, and updated photos are available for your review in our investor portal.




JULY 2025




Highlights from this month include:
- Completion of the roof installation
- Exterior finish (EIFS) along the west and south elevations
- Hallway systems installation on the second floor
- Guardrails and handrails in stairwells
- Installation of HVAC drain pans, refrigerant lines, condensers, and ductwork
- Electrical trim and lift station installation
JUNE 2025




MAY2025






APRIL 2025